Navigation:Refrigeration/cooling/refrigeration equipment engineering-Shanghai Ying Xiang refrigeration equipment limited >> News >>

Code for cooling design room design, equipment arrangement, and other

Release time:2016-10-12 16:01:45
Refrigeration room cooling load in as close to the Center layout, and should meet the following requirements:
 
And freon-compression refrigeration device, can be arranged in the civil construction, production plant and auxiliary buildings, but not directly assigned in the stairwellentrances, hallways and buildings;
Second, ammonia compression refrigeration unit should be arranged in the open room partitions or in separate buildings, but no arrangement within the auxiliary buildings of civil and industrial enterprises;
 
Note:
1, auxiliary equipment can be arranged outdoors.
2, ammonia refrigeration room fire safety requirements, should be in force in the country of the implementation of the code for fire protection design of buildings.
Third, the steam jet refrigeration, outdoor design. Lithium bromide absorption refrigeration, should be arranged in the building, when conditions permit, outdoor design. Open layout, the refrigeration unit electrical equipment and control instrumentation, shall be located indoors.
 
Refrigeration room equipment layout and piping connections should comply with the process, and should be easy to install, operate, maintain and repair:
 
Refrigerator overhang and distance between the Distributor and the width of the main channel, should be not less than 1.5M distance between the refrigerator and thewall and not the main channel of width, shall be not less than 0.8M.
 
Note:
1, and used for maintenance of channel width should be determined according to the type of equipment and specifications.
2, arrangement of horizontal shell and tube evaporators, chillers and when lithium-bromide absorption-type refrigerating machines, should consider the possibility of clean or replace the tubes.
 
Refrigeration room height should be determined according to the equipment, and should meet the following requirements:
 
, Freon compressing refrigeration should not be less than 3.6M;
Second, for ammonia compression refrigeration should not be less than 4.8M;
Third, in lithium-bromide absorption-type refrigerating equipment distance of the top of roof or floor shall not be less than 1.2M.
Note, the refrigeration room height, means from the ground to the roof or floor height.
 
Refrigerator in room hues and auxiliary equipment and water pumps are spaced between and depending on the circumstances, set the guards ' room, maintenance, storage rooms, toilets and other facilities.
 
Ammonia refrigeration room setting two export directly to foreign as possible fromeach other, and should be from the Interior to the outside door.
Ammonia refrigeration room power switch be located near the outer door. When the accident occurred, should have the possibility of immediately cut off the power supply, but the accident power supply shall not be cut off.
 
Ammonia refrigeration room; should also set the necessary fire and safety equipment (such as fire extinguishers and gas masks, etc).
Set up centralized heating and refrigeration room, the indoor temperature should not be below 15 ºc. Ammonia refrigeration room is strictly prohibited to use fire heating.
Refrigeration room shall have a water supply and sewerage facilities, necessary for the times set up a phone.
 
Following refrigeration equipment and piping insulation:
 
A suction, compression chiller pipe, liquid supply pipe between the evaporator andexpansion valve;
II, lithium bromide absorption refrigerating machine generator, solution heat exchangers, evaporators, cooling water pipes;
Third, steam jet refrigerating evaporator and main injector head;
Four, cold water pipes and cold water tank;
Five of heat supply pipeline and condensate pipe, refrigeration equipment.
 
Equipment and piping insulation shall comply with the following requirements:
 
First, the outer surface of the insulation shall not produce condensation water;
Second, the surfaces of the insulation shall have a vapor-proof layer;
C, pipe and bracket should be taken to prevent "cold bridges" measures